Ohio School Facilities Construction Project |
|
| September 2007 Update | |
|
- CM has received the Construction Document Phase Submission from the Design Team. The OSDM Compliance, Constructability, and Budget Analysis is in progress. § New Elementary/Middle School – Bid - New Elementary/Middle School Facility Bid Package(s) were bid on September 25th. - Post Bid Interviews are scheduled to occur October 2nd & 3rd with each of the ‘Apparent Low’ Bidders. Post Bid Interviews help to determine whether the ‘Apparent Low’ Bidder is capable of completing the scoped work. § New Elementary/Middle School Early Site Package - The Early Site Package contains all earthwork and sub-grade utility work necessary to prepare the site for the new facility. This includes engineering of the sub-base at the facility’s “footprint”, ensuring that the soils supporting the structure will be sufficient. - The Facility’s ‘Footprint’ has been completed to the sub-grade elevation. - Site Utilities are 95% complete. - Asphalt is scheduled to be installed the week of October 1st. § High School Early Site Utilities Package - The Early Site Utilities Package consists of the sub-grade utility work necessary to accommodate remaining facilities after the existing High School is demolished. - The Early Site Utility Package is 98% complete. § High School Asbestos Abatement Package - The Asbestos Abatement Package at the High School is 100% complete. § High School Demolition & Site Improvement Package - The Demolition & Site Improvement Package consists of demolition of the current High School and select surrounding structures. The package also consists of preparation of the facility’s footprint and surrounding sub-grade. - The Front Entrance is scheduled to remain, along with the Conley Center and Tank Memorial Stadium.
-
The Demolition & Site Improvement Package is scheduled to
begin in late October. |
|
| May 2007 Update | |
|
§ New High School Schematic Design Phase Submission - Approved and Executed § New Elementary/Middle School Design Development Phase Submission - Submitted by Design Team and Review Completed by Project Team - Design Development expounds (builds upon) those Design Principles developed at the Schematic Design Phase. Design Development illustrates all of the intricacies of the designed – Mechanical Systems, Loose Furnishings, Electrical/Technological Systems, etc. § New Elementary/Middle School Early Site Package - The Early Site Package contains all earthwork and sub-grade utility work necessary to prepare the site for the new facility. This includes engineering of the sub-base at the facility’s “footprint”, ensuring that the soils supporting the structure will be sufficient. - Permitting for Site Work Submitted & Approved by State of Ohio - Bid Opening Successful - Work Scheduled to Begin Memorial Day Week § High School Early Site Utilities Package - The Early Site Utilities Package consists of the sub-grade utility work necessary to accommodate remaining facilities after the existing High School is demolished. - Preliminary Bid Documents have been submitted and are under review by the Project Team. - The following are dates of interest: ü Bid Package Advertisement → May 20th & 27th, 2007 ü Pre-Bid Meeting → May 24, 2007 ü Bid Opening → June 5, 2007 |
|
| March 2007 Update | |
|
New Elementary/Middle School Schematic Design Phase Submission
New Elementary/Middle School Design Development Phase Submission
New Elementary/Middle School Early Site Package
- Dates of Interest: ü April 1st & 8th – Bid Advertisements run in Newspaper(s) ü April 10th – Pre-Bid Meeting
ü
April 24th – Bid Opening |
|
| February 2007 Update | |
Accurate Surveys of All Properties Completed
Final Geotechnical Studies Conducted
Asbestos Evaluation Completed
Schematic Design Completed for Elementary/Middle and High School Facility
Project Team Design Sessions Currently Being Conducted
Construction Testing Agent Approved
|
|
|
|