Ohio School Facilities Construction Project

  September 2007 Update
 


  §               New High School Construction Document Phase Submission

-        CM has received the Construction Document Phase Submission from the Design Team.  The OSDM Compliance, Constructability, and Budget Analysis is in progress. 

§               New Elementary/Middle School Bid

-        New Elementary/Middle School Facility Bid Package(s) were bid on September 25th.

-        Post Bid Interviews are scheduled to occur October 2nd & 3rd with each of the ‘Apparent Low’ Bidders.  Post Bid Interviews help to determine whether the ‘Apparent Low’ Bidder is capable of completing the scoped work. 

§               New Elementary/Middle School Early Site Package

-        The Early Site Package contains all earthwork and sub-grade utility work necessary to prepare the site for the new facility.  This includes engineering of the sub-base at the facility’s “footprint”, ensuring that the soils supporting the structure will be sufficient.

-        The Facility’s ‘Footprint’ has been completed to the sub-grade elevation.

-        Site Utilities are 95% complete.

-        Asphalt is scheduled to be installed the week of October 1st

§               High School Early Site Utilities Package

-        The Early Site Utilities Package consists of the sub-grade utility work necessary to accommodate remaining facilities after the existing High School is demolished.

-        The Early Site Utility Package is 98% complete. 

§               High School Asbestos Abatement Package

-        The Asbestos Abatement Package at the High School is 100% complete. 

§               High School Demolition & Site Improvement Package

-        The Demolition & Site Improvement Package consists of demolition of the current High School and select surrounding structures.  The package also consists of preparation of the facility’s footprint and surrounding sub-grade.

-        The Front Entrance is scheduled to remain, along with the Conley Center and Tank Memorial Stadium.

-        The Demolition & Site Improvement Package is scheduled to begin in late October.
 

  May 2007 Update
 
 
§               New High School Schematic Design Phase Submission

-        Approved and Executed

  §               New Elementary/Middle School Design Development Phase Submission

-        Submitted by Design Team and Review Completed by Project Team

-        Design Development expounds (builds upon) those Design Principles developed at the Schematic Design Phase.  Design Development illustrates all of the intricacies of the designed – Mechanical Systems, Loose Furnishings, Electrical/Technological Systems, etc.

  §               New Elementary/Middle School Early Site Package

-        The Early Site Package contains all earthwork and sub-grade utility work necessary to prepare the site for the new facility.  This includes engineering of the sub-base at the facility’s “footprint”, ensuring that the soils supporting the structure will be sufficient.

-        Permitting for Site Work Submitted & Approved by State of Ohio

-        Bid Opening Successful

-        Work Scheduled to Begin Memorial Day Week

     §               High School Early Site Utilities Package

-        The Early Site Utilities Package consists of the sub-grade utility work necessary to accommodate remaining facilities after the existing High School is demolished.

-        Preliminary Bid Documents have been submitted and are under review by the Project Team.

-        The following are dates of interest:

ü      Bid Package Advertisement → May 20th & 27th, 2007

ü      Pre-Bid Meeting → May 24, 2007

ü      Bid Opening → June 5, 2007

   
  March 2007 Update
 


New High School Schematic Design Phase Submission

  • Review Completed and Awaiting Approval/Execution

New Elementary/Middle School Schematic Design Phase Submission

  • Review Completed and Phase Submission Approved/Executed

New Elementary/Middle School Design Development Phase Submission

  • Submitted by Design Team and Under Review by Project Team

  • Design Development expounds (builds upon) those Design Principles developed at the Schematic Design Phase.  Design Development illustrates all of the intricacies of the designed – Mechanical Systems, Loose Furnishings, Electrical/Technological Systems, etc.

 New Elementary/Middle School Early Site Package

  • The Early Site Package contains all earthwork and sub-grade utility work necessary to prepare the site for the new facility.  This includes engineering of the sub-base at the facility’s “footprint”, ensuring that the soils supporting the structure will be sufficient. 

  • Permitting for Site Work Submitted & Approved by State of Ohio

-        Dates of Interest:

ü      April 1st & 8th – Bid Advertisements run in Newspaper(s)

ü      April 10th – Pre-Bid Meeting

ü      April 24th – Bid Opening
 

  February 2007 Update
 


Rendering and Floor Plan of New Facilities

Accurate Surveys of All Properties Completed

  • Topographical Surveys
  • ALTA Boundary Surveys

Final Geotechnical Studies Conducted

  • Defines the type of soil through multiple core drillings.  Provides data to assure that the building site is sufficient to support the structure to be built.

Asbestos Evaluation Completed

  • Defines hazardous materials that must be removed prior to demolition

Schematic Design Completed for Elementary/Middle and High School Facility

  • First draft of building blueprints

Project Team Design Sessions Currently Being Conducted

  • School employees are meeting with interior designers and architects to assure that the new facilities meet the educational needs of the future.

Construction Testing Agent Approved

  • Ohio School Facilities Commission requires the employment of a construction testing agent in order to test and assure that the materials used are of high quality during the construction process. (ex. Soil, Concrete, Rebar Steal, Footers, Welds, etc)